dbTalk Databases Forums  

scheduling events in ASA11

sybase.public.sqlanywhere.general sybase.public.sqlanywhere.general


Discuss scheduling events in ASA11 in the sybase.public.sqlanywhere.general forum.



Reply
 
Thread Tools Display Modes
  #1  
Old   
Chris Werner
 
Posts: n/a

Default scheduling events in ASA11 - 09-23-2009 , 05:05 AM






Hi,

using ASA 9 I'm used to schedule an event using SC:
"Properties" popup menu entry, "Conditions" tab, Radio
Button "By the following schedules", clicking the "New"
button and make my choice using a calendar dialog. How
to do that in SC for ASA 11.0.1?

TIA

Chris Werner
f+s software gmbh

Reply With Quote
  #2  
Old   
Nick Elson [Sybase iAnywhere]
 
Posts: n/a

Default Re: scheduling events in ASA11 - 09-23-2009 , 08:57 AM






To change an existing event's schedule you navigate
to the event, double-click on that to see it's SQL
definition and in the right pane there will be "Schedules"
tab to the right of the active "SQL" tab that is
currently active. [these tabs are at the top of the right
panel]

When creating a new event picking the event type
as scheduled will cause the event type as
scheduled will cause the wizard to present you
with the scheduling dialogs soon after that.

HTH
"Chris Werner" <cwAT{PleaseNoSpam}f-s.de> wrote

Quote:
Hi,

using ASA 9 I'm used to schedule an event using SC:
"Properties" popup menu entry, "Conditions" tab, Radio
Button "By the following schedules", clicking the "New"
button and make my choice using a calendar dialog. How
to do that in SC for ASA 11.0.1?

TIA

Chris Werner
f+s software gmbh

Reply With Quote
  #3  
Old   
Chris Werner
 
Posts: n/a

Default Re: scheduling events in ASA11 - 09-23-2009 , 09:22 AM



Thanks a lot Nick, found it. Must be something in the coffee ...


"Nick Elson [Sybase iAnywhere]" <@nick@.@elson@@sybase@.@com@> schrieb im
Newsbeitrag news:4aba2930$1 (AT) forums-1-dub (DOT) ..
Quote:
To change an existing event's schedule you navigate
to the event, double-click on that to see it's SQL
definition and in the right pane there will be "Schedules"
tab to the right of the active "SQL" tab that is
currently active. [these tabs are at the top of the right
panel]

When creating a new event picking the event type
as scheduled will cause the event type as
scheduled will cause the wizard to present you
with the scheduling dialogs soon after that.

HTH
"Chris Werner" <cwAT{PleaseNoSpam}f-s.de> wrote in message
news:4ab9f2e1$1 (AT) forums-1-dub (DOT) ..
Hi,

using ASA 9 I'm used to schedule an event using SC:
"Properties" popup menu entry, "Conditions" tab, Radio
Button "By the following schedules", clicking the "New"
button and make my choice using a calendar dialog. How
to do that in SC for ASA 11.0.1?

TIA

Chris Werner
f+s software gmbh



Reply With Quote
Reply




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off



Powered by vBulletin Version 3.5.3
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.