You must move the entire database. To move just one cube, your only option
is to cut & paste the metadata and then do a full reprocess.
--
Dave Wickert [MS]
dwickert (AT) online (DOT) microsoft.com
Program Manager
BI Practices Team
SQL BI Product Unit (Analysis Services)
--
This posting is provided "AS IS" with no warranties, and confers no rights.
"Daniela Binatti" <anonymous (AT) discussions (DOT) microsoft.com> wrote
Quote:
Can I move just one cube?
I have two servers: the olap server and another one, which is more
powerful than the first. The second one I'm using to execute the full
|
process because it's faster.... but the execution takes more than a day. So,
I move one cube at a time to the production server and that's why I can't
archive and restore all the database.
Quote:
Is there any other possibility??
Thank you very much.
Daniela Binatti. |