dbTalk Databases Forums  

Drillthrough option

microsoft.public.sqlserver.olap microsoft.public.sqlserver.olap


Discuss Drillthrough option in the microsoft.public.sqlserver.olap forum.



Reply
 
Thread Tools Display Modes
  #1  
Old   
AshVsAOD
 
Posts: n/a

Default Drillthrough option - 04-18-2004 , 06:43 PM






Hello,

I am using the drillthrough option on a cube to see the underlying data,
however it only works on the All Periods (time dimension). If I change the
period to be a specific date it fails.. Is there a way to enable
drillthrough on all descendants of time?



Reply With Quote
  #2  
Old   
Yuan Shao
 
Posts: n/a

Default RE: Drillthrough option - 04-19-2004 , 09:24 AM






Hello,

Do you mean you failed to drill through the cell when you change the period
to be a specific date? In the Sample database FordMart 2000, I performed
some tests on the sales cube with Time dimension having the date level. It
seems I am able to drill through the cell when the period to be a specific
date. It is appreciated you can repro the same problem on FoodMart 2000.

In addition, I found the following article for your reference.
How to specify drillthrough options for a regular cube
http://msdn.microsoft.com/library/de...us/olapdmad/ag
htcubopt_6pnp.asp

Thank you,

Michael Shao
Microsoft Online Partner Support
Get Secure! - www.microsoft.com/security
This posting is provided "as is" with no warranties and confers no rights.


Reply With Quote
  #3  
Old   
AshVsAOD
 
Posts: n/a

Default Re: Drillthrough option - 04-19-2004 , 05:12 PM



Michael, and other experts.

That is what I mean. If I leave the Period dimension at the All level I can
drill through perfectly fine. However if I change this Period dimension to
anything other than All I receive the following error message.

Unable to drill through.
Data source provider error. Incorrect syntax near the keyword 'from'.;42000

I have checked within FoodMart2000 and it seems I can drill down on the demo
cube at all date levels. What am I doing wrong?

My cube is very simple... A single fact table..
With one measure = Units..
3 dimensions Period, Leave Type, Employee..

Any assistance would be greatly appreciated.

Clint




""Yuan Shao"" <v-yshao (AT) online (DOT) microsoft.com> wrote

Quote:
Hello,

Do you mean you failed to drill through the cell when you change the
period
to be a specific date? In the Sample database FordMart 2000, I performed
some tests on the sales cube with Time dimension having the date level. It
seems I am able to drill through the cell when the period to be a specific
date. It is appreciated you can repro the same problem on FoodMart 2000.

In addition, I found the following article for your reference.
How to specify drillthrough options for a regular cube

http://msdn.microsoft.com/library/de...us/olapdmad/ag
htcubopt_6pnp.asp

Thank you,

Michael Shao
Microsoft Online Partner Support
Get Secure! - www.microsoft.com/security
This posting is provided "as is" with no warranties and confers no rights.




Reply With Quote
  #4  
Old   
AshVsAOD
 
Posts: n/a

Default Re: Drillthrough option - 04-19-2004 , 05:42 PM



Michael,

I have found a post you made regarding this problem on the following web
page:

http://www.webservertalk.com/message167209.html

I will see if changing to ODBC rather than OLE DB fixes the issue.
"AshVsAOD" <.> wrote

Quote:
Michael, and other experts.

That is what I mean. If I leave the Period dimension at the All level I
can
drill through perfectly fine. However if I change this Period dimension
to
anything other than All I receive the following error message.

Unable to drill through.
Data source provider error. Incorrect syntax near the keyword
'from'.;42000

I have checked within FoodMart2000 and it seems I can drill down on the
demo
cube at all date levels. What am I doing wrong?

My cube is very simple... A single fact table..
With one measure = Units..
3 dimensions Period, Leave Type, Employee..

Any assistance would be greatly appreciated.

Clint




""Yuan Shao"" <v-yshao (AT) online (DOT) microsoft.com> wrote in message
news:R5s4MohJEHA.3564 (AT) cpmsftngxa10 (DOT) phx.gbl...
Hello,

Do you mean you failed to drill through the cell when you change the
period
to be a specific date? In the Sample database FordMart 2000, I performed
some tests on the sales cube with Time dimension having the date level.
It
seems I am able to drill through the cell when the period to be a
specific
date. It is appreciated you can repro the same problem on FoodMart 2000.

In addition, I found the following article for your reference.
How to specify drillthrough options for a regular cube


http://msdn.microsoft.com/library/de...us/olapdmad/ag
htcubopt_6pnp.asp

Thank you,

Michael Shao
Microsoft Online Partner Support
Get Secure! - www.microsoft.com/security
This posting is provided "as is" with no warranties and confers no
rights.






Reply With Quote
  #5  
Old   
AshVsAOD
 
Posts: n/a

Default Re: Drillthrough option - 04-19-2004 , 05:52 PM



Sorry for the multitude of posts. After changing to ODBC the problem is
resolved. Thanks!!!
"AshVsAOD" <.> wrote

Quote:
Michael,

I have found a post you made regarding this problem on the following web
page:

http://www.webservertalk.com/message167209.html

I will see if changing to ODBC rather than OLE DB fixes the issue.
"AshVsAOD" <.> wrote

Michael, and other experts.

That is what I mean. If I leave the Period dimension at the All level I
can
drill through perfectly fine. However if I change this Period dimension
to
anything other than All I receive the following error message.

Unable to drill through.
Data source provider error. Incorrect syntax near the keyword
'from'.;42000

I have checked within FoodMart2000 and it seems I can drill down on the
demo
cube at all date levels. What am I doing wrong?

My cube is very simple... A single fact table..
With one measure = Units..
3 dimensions Period, Leave Type, Employee..

Any assistance would be greatly appreciated.

Clint




""Yuan Shao"" <v-yshao (AT) online (DOT) microsoft.com> wrote in message
news:R5s4MohJEHA.3564 (AT) cpmsftngxa10 (DOT) phx.gbl...
Hello,

Do you mean you failed to drill through the cell when you change the
period
to be a specific date? In the Sample database FordMart 2000, I
performed
some tests on the sales cube with Time dimension having the date
level.
It
seems I am able to drill through the cell when the period to be a
specific
date. It is appreciated you can repro the same problem on FoodMart
2000.

In addition, I found the following article for your reference.
How to specify drillthrough options for a regular cube



http://msdn.microsoft.com/library/de...us/olapdmad/ag
htcubopt_6pnp.asp

Thank you,

Michael Shao
Microsoft Online Partner Support
Get Secure! - www.microsoft.com/security
This posting is provided "as is" with no warranties and confers no
rights.








Reply With Quote
Reply




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off



Powered by vBulletin Version 3.5.3
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.