Default 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-15-2008 , 04:36 PM






I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the SQL
Server Agent state = offline and they will not come online until i start the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren

Reply With Quote
  #2  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM






Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #3  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #4  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #5  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #6  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #7  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #8  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #9  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
  #10  
Old   
Nirmal Sharma
 
Posts: n/a

Default Re: 2 Node Active/Active SQL 2005 Enterpise Cluster - 04-16-2008 , 11:09 AM



Do you start the Cluster Service on Node A or Node B?

"Darren" <Darren (AT) discussions (DOT) microsoft.com> wrote

Quote:
I have a two node active/active cluster setup. when i stop the cluster
service one node A all resources fail over to the other node B, but the
SQL
Server, SQL Server Fulltext and Analysis Services state = failed and the
SQL
Server Agent state = offline and they will not come online until i start
the
cluster service on Node A and all the resources fail back and all services
come back online. Anybody have any ideas?

thanks,

Darren



Reply With Quote
Reply




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off



Powered by vBulletin Version 3.5.3
Copyright ©2000 - 2012, Jelsoft Enterprises Ltd.